|
n Fort Green
FGH 6 & 7 was a 995 acre project for IMC Phosphates Company which consisted
of the placement of 20 million cubic yards of sand, the
construction of over 500 acres of wetland construction requiring
the excavation and placement of over 500,000 cubic yards of muck
material, construction of 400 acres of xeric scrub habitat, and 50
acres of stream bed construction. The project was completed six
months ahead of schedule.
n Four Corners
Reclamation was a 152 acre project with a 60 acre
wetland mitigation requirement, consisting of the movement of over
1 million cubic yards of overburden, finish grading, and placement
of over 35,000 cubic yards of organic muck in the wetland. The
project was completed 60 days ahead of the required schedule.
n Oak Hammock
Landfill is one the largest regional landfills in the
Southeast. BHC was contracted by Lundquist Excavating to construct
the storm water berms, ponds, and earthwork and clearing associated
with the construction of Cell 1A and Cell 1B which required over
two (2) million cubic yards of material to be moved. In spite of
one of the wettest summers on record, the project was completed and
opened as projected. We were subsequently tasked with the
preparation of a 36 acre borrow area, the construction of entry
roads and the construction of Cell 4 which required the placement
of over 250,000 cubic yards in 40 days. The project was completed
16 days ahead of schedule.
n Cargill’s
WRG-BL-06 Old Lands Reclamation project consisted of
the reclamation of 400 acres of mined out land, requiring
construction of approximately 200 acres of wetlands, and 200 acres
of uplands. Construction required the excavation of almost 1.5
million cubic yards of sand and overburden, grassing of 200 acres of
uplands, clay consolidation, and weir/spillway construction. The
project was completed 12 months ahead of schedule.
n Northwest
Spray Irrigation Field project consisted of approximately
65 acres of rapid infiltration basin construction which required the
excavation and placement of over 400,000 cubic yards of sand
material. The project was completed four months ahead of schedule.
n Tenoroc
Maintenance Contract project has been ongoing for over 3 years
and consists of assisting the Florida Department of Environmental
Protection and Florida Wildlife Conservation in clearing, ditching,
clay consolidation, lake interconnects, and drainage systems in a
6000 acre reserve including the Saddle
Creek Basin in Polk County.
n
Noralyn Mine
Reclamation required the reclamation of 900 acres of clay
settling areas, including the consolidation of over 800 acres of
clay and the excavation of over 1 million cubic yards of
overburden, construction of outfall weirs, grassing, fencing and
tree planting. The project was completed six months ahead of the
original schedule.
|


|
n
Hurricane Debris Handling at All
Polk County Landfills Bul-Hed
Corporation was tasked with an Emergency Order to mobilize
equipment to all landfills in Polk County
a few hours after Hurricane Charlie hit in 2004. Task Orders
included the construction of dump areas, handling debris at the
cells, and construction of new FDOT turning lanes. The turning
lanes construction began on Saturday morning and was completed 36
hours later! We were tasked with the construction of a new Class
III cell at the North Central Landfill which was completed in less
than 10 days from the start of construction to the time of
completion. As of December 1, 2004, over 2 million cubic yards of
debris had been delivered to the Polk County
sites.
n
n
|
Click on
thumbnail to view
larger
image

|
n
North Lake Parker Wetlands is a Florida Department of
Environmental Protection project, managed by Florida
Wildlife Commission, and required the excavation of 300,000 cubic
yards of material in constructing a wetland system that connects
several lakes in the Tenoroc Wildlife Management Area, Lake Gibson
and eventually Lake
Parker. We
were subsequently tasked with the construction of an access
roadway, boat ramps, and parking areas. The project was completed
six months ahead of schedule.
n
Nocatee Parkway is the
largest private roadway development ever contracted in Florida.
Bul-Hed was contracted by Barco-Duval Engineering to perform the
clearing and grubbing which consisted of over 500 acres. Over 200
acres was completed in less than three weeks which advanced the
overall schedule for the project by over 30 days.
|
Click on thumbnail to view larger image
|

|

|

|
|
Click on
thumbnail to view
larger
image

|
n
Wal-Mart
Regional Distribution Center required the excavation and
placement of over 800,000 cubic yards of material for the
construction of the warehouse buildings and parking areas. Bul-Hed
was contracted by Hewitt Contracting Company to perform
approximately 60% of the excavation.
n Robinson
Preserve is a project for Manatee
County that is intended
to create a canoe path from the Manatee River to Perico Bayou with a
series of wetland restoration areas, a trail system, three timber
vehicular bridges, boardwalks, observation towers, wetland
plantings, power line and water line relocations, and observation
mounds. Bul-Hed has been recognized by the funding agencies for its
sensitivity and protection of the existing mangroves, water
quality, eagles’ nest, and the environment in general. The project
required the excavation of over 600,000 cubic yards of material and
200 acres of clearing. The earthwork was completed in half of the
allowed contract time. For
more information on this project please visit the following link: http://www.co.manatee.fl.us
|
Click on thumbnails
to see larger photos of Project
|
Preconstruction
Photos
|

|

|

|
|
|
Construction
Progress
Photos
|

|

|

|
|
|
|

|

|

|
|
|
Construction
Final
Photos
|

|

|

|
|
|
|
|
|
|
n Alcoa Ft.
Meade was a very unique remediation contract. The general scope
of work required the import and placement of 100,000 CY of sandy
material. This was the first phase of a surcharge plan
to cap an abandoned silica solids settling pond. These solids
were a by-product of the former Ft. Meade Works that manufactured
aluminum fluoride from fluorsilicic acid and alumina
trihydate. Alcoa’s safety program requirements and job
specifications exceed many contractors’ ability and record to bid
on the project. Bul-Hed Corporation was chosen for this project
because of its outstanding safety record and commitment to
developing a site specific safety plan that exceeded Alcoa’s
specifications. In addition, the contract required that the
surcharge material be placed within 60 days. The job was
closed out in 40 days.
|
|
Click on thumbnails
to see larger photos of Project
|

|

|

|
|